Duplicate an Activity

Activities can be very similar to one another, so to save time you can create copies of activities.

Written by Hylet Pistorius
Updated over a month ago

As a stakeholder or administrator, editing a process or value stream, you can duplicate an activity within a process/value stream.

Quick Steps

  1. Open the activity options using any of the following methods:

    1. Click the Options icon on the activity on the map

    2. Click the Options icon in the right-hand diagram menu

    3. Right-click the activity on the map

  2. Select Duplicate.

  3. The Duplicate Node window appears:

    1. Choose the process/value stream where the activity must be copied (current or another one)

    2. Update the activity title if required

    3. Click Duplicate to confirm

  4. The copied activity is added to the end of the selected map.

To edit the newly duplicated activity, read more here.